Hi,

Is it possible to have a task common to two project files (i.e. linked), and
if a task changes in one, there is some kind of notification before the
change is accepted?

For example, if we had a 'master' schedule containing major milestones, and
a number of 'sub' schedules that needed to contain the tasks relating to the
milestone (managed by individuals), can project notify the owner of the
master schedule when a dependent task changes (is 'requested' to change)? Not
just a automatic change as with normal cross project links.

Thanks.
 
G

Gary L. Chefetz \(MVP\)

Dylan:

In a sense, all such changes are requests in that anytime a PM opens a
project with external links that cause a schedule change, the application
notifies you and asks for your acceptance. There's no other workflow behind
it. Rejecting the change preserves the dates in the current plan, but
doesn't send a rejection back to the original plan. You need PMs working
together to control such events.

--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

-
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top