G
Gary Anderson
I have questions regarding linking tasks between projects:
1. How do I get a good clear critical path when I am
linking tasks between multiple schedules? The consolidated
schedule does not give a very clear critical path.
2. What are the pros/cons of linking multiple schedules
vs. using one large schedule?
3. How can I roll up resources from multiple linked
schedules into a top level summary for a total program?
4. Is there a list of Microsoft Project consultants
available?
1. How do I get a good clear critical path when I am
linking tasks between multiple schedules? The consolidated
schedule does not give a very clear critical path.
2. What are the pros/cons of linking multiple schedules
vs. using one large schedule?
3. How can I roll up resources from multiple linked
schedules into a top level summary for a total program?
4. Is there a list of Microsoft Project consultants
available?