C
chris
I'm linking multiple tasks between projects. I have found that when I link a task the corresponding task from the other project is inserted above the task being linked. When this happens a new task ID number is inserted and I have found that previous dependencies I had set up are now linked incorrectly because the numbers have changed. Is there a way t
1) either get the linked task not to be inserted or 2) to not allow it to increase the task number (ie; use the same task # as being linked from) to avoid the problem with the numbers changing and the old links now being invalid
Thank
1) either get the linked task not to be inserted or 2) to not allow it to increase the task number (ie; use the same task # as being linked from) to avoid the problem with the numbers changing and the old links now being invalid
Thank