Linking tasks from multiple projects

Y

Yasser Batsh

I have created a solution where i save 'projects / tasks / task dependencies'
in my own database and use microsoft project automation to calculate dates of
these projects / tasks.
What i need to do to to link between different tasks in different projects.
i thought of the following solution:
After adding dependencies between these tasks at the application level , i
send all the tasks from all involved projects to MS Project and do the
calculations required. Yet, i still have the following difficulties:
Each of my project has different schedule date, and when i send all tasks to
MSP, the dates of tasks that are not yet started will follow the date of the
current project which is not the case when each project is calculated alone...

Any one who can help me in this or suggest a different idea ?

Thanks,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top