Linking tasks in MS Project 2007

S

shoppingboy

roI have copied 5 tasks from a project and linked them in a consolidate
project using the 'Paste Special' command. This almost works wel
because any changes I make to the tasks in the original project ar
reflected in the consolidated project except the % complete shown in th
indicators column. For some reason, when I make any changes to the
complete in the original project, the changes arent reflected in th
consolidated project (and vice versa). I'm presuming that % complet
should be updated like any other field therefore any help would b
appreciated
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top