G
GeorgeD
I have a number of detail projects that want to group into a larger
summary project, with just the summary lines from the detail groups.
when I link the tasks, using the methods in all of the Help files, I
get an entry in both schedules, which it don't want. I also get the
information in the summary schedule, but not the work updates, just
the durations.
What i am looking for this:
Project Detail
Duration
Work Pred.
Detail summary 3 Days 6 hours
Task A 1 day 2
hours
Task B 1 day 2
hours Task A
Task C 1 day 2
hours Task B
when I link Detail Summary into Project Summary, I get something like
this
Project Summary 3 Days 0 hours
detail summary 3 Days 6 Hours
Project summary Task line 0 days 0 hours
I want the project Summary to reflect the duration of 3 days, which it
appears to do, and the work to be refelected, so when i add detail
project 2 and detail project 3 and detail project 4, and so on, i can
get an idea of how i am doing for all of the detail projects.
any ideas?
summary project, with just the summary lines from the detail groups.
when I link the tasks, using the methods in all of the Help files, I
get an entry in both schedules, which it don't want. I also get the
information in the summary schedule, but not the work updates, just
the durations.
What i am looking for this:
Project Detail
Duration
Work Pred.
Detail summary 3 Days 6 hours
Task A 1 day 2
hours
Task B 1 day 2
hours Task A
Task C 1 day 2
hours Task B
when I link Detail Summary into Project Summary, I get something like
this
Project Summary 3 Days 0 hours
detail summary 3 Days 6 Hours
Project summary Task line 0 days 0 hours
I want the project Summary to reflect the duration of 3 days, which it
appears to do, and the work to be refelected, so when i add detail
project 2 and detail project 3 and detail project 4, and so on, i can
get an idea of how i am doing for all of the detail projects.
any ideas?