S
Sumit
Hi,
This is a manufacturing scenario where I need to identify start date for
ordering material and other tasks based on the start date of manufacturing.
Let's assume there are 5 tasks:
1. Define Packaging specification - 2 weeks
2. Issue Purchase Order(s) to external manufacturer - 2 day
3. Order, receive & test raw material - 1 month
4. Manufacture - 1 month
5. Test and report on manufacture - 2 weeks
Task 1 should start 3 months before 4,
Task 2 should start 2 month before 4,
Task 3 should start 1 month before 4, and
Task 5 should finish 3 months after 4.
I configured above by making Task 1 as predecessor of 4 (Start to Start) and
a lead time of 3 months and similar with Task 2 and 3. I made task 4
predecessor of Task 5 with Finish to Finish relationship and a lag time to 3
months.
This worked fine until i gave a start date to project. The moment i do this,
MS Project assigns project start date to Task 4 and backward schedules Task
1,2 & 3 and they are scheduled to start even before project start date.
The requirement is to get earliest start date for manufacture based on
project start date. How do I achieve this? Ideally earliest predecessor
should get project start date and rest should get spread based on lead time
but this is not how MS Project schedules.
Am I missing something? Any thoughts?
Regards,
Sumit.
This is a manufacturing scenario where I need to identify start date for
ordering material and other tasks based on the start date of manufacturing.
Let's assume there are 5 tasks:
1. Define Packaging specification - 2 weeks
2. Issue Purchase Order(s) to external manufacturer - 2 day
3. Order, receive & test raw material - 1 month
4. Manufacture - 1 month
5. Test and report on manufacture - 2 weeks
Task 1 should start 3 months before 4,
Task 2 should start 2 month before 4,
Task 3 should start 1 month before 4, and
Task 5 should finish 3 months after 4.
I configured above by making Task 1 as predecessor of 4 (Start to Start) and
a lead time of 3 months and similar with Task 2 and 3. I made task 4
predecessor of Task 5 with Finish to Finish relationship and a lag time to 3
months.
This worked fine until i gave a start date to project. The moment i do this,
MS Project assigns project start date to Task 4 and backward schedules Task
1,2 & 3 and they are scheduled to start even before project start date.
The requirement is to get earliest start date for manufacture based on
project start date. How do I achieve this? Ideally earliest predecessor
should get project start date and rest should get spread based on lead time
but this is not how MS Project schedules.
Am I missing something? Any thoughts?
Regards,
Sumit.