K
Karuuna
Hi,
I just had a question about linking tasks in project 2007. When we link two
or more projects, each linkage produces an extra line in the master project.
So, if I link the same task in eight different projects, does that mean the
master plan will have 8 extra lines to show those links?
I just had a question about linking tasks in project 2007. When we link two
or more projects, each linkage produces an extra line in the master project.
So, if I link the same task in eight different projects, does that mean the
master plan will have 8 extra lines to show those links?