Linking tasks into master project

R

Robin

I know how to create a master project with sub projects
linked. However, I'm not sure how to have a master
project and only link level 1 and 2 tasks. Can someone
walk me through it? Thanks.
 
R

Rob Schneider

It's really all or nothing. When you insert the subproject, the entire
project is linked. Can avoid looking at tasks level 3 and below by
simply not opening that level of the hierarchy.

Hope this is useful to you. Let us know.

rms
 
G

Gérard Ducouret

Hello Robin,
I'm not sure about what you want, but have you tried the "Indent" button in
the tool bar (Green rightward arrow)
Hope this helps,

Gérard Ducouret
 
R

Robin

Thanks, I knew that I could hide and/or indent tasks. I
thought perhaps I could just set up a link for specific
tasks from a sub project. Thanks!
 
M

Mike Glen

Hi Robin,

If you expand the sub-project files within the master, you can link tasks in
the normal way: eg select the 2 tasks an click the Link tool.

Mike Glen
Project MVP
 