L
Lucinda Brookens
Hi Jeremy:
Well, I would schedule all of these tasks with finish-to-
finish relationships (so that they schedule to complete
on the same date). This way you can enter the actual
start dates for each task.
Hope this helps!
order the pages are coded in, so when I link them all
together it seems as if one has to be coded right after
the other, in order, and so on... Is there a way to tell
Project that all of these tasks just have to be done
within 10 days or something like that, and the order they
are completed doesn't matter? Or should I just schedule
them one after the other and when I actually complete
them I will update the ACTUAL dates? Thanks!!
Well, I would schedule all of these tasks with finish-to-
finish relationships (so that they schedule to complete
on the same date). This way you can enter the actual
start dates for each task.
Hope this helps!
header "Admin Pages to be coded". I don't care what-----Original Message-----
I have a list of about 10 tasks underneath a
order the pages are coded in, so when I link them all
together it seems as if one has to be coded right after
the other, in order, and so on... Is there a way to tell
Project that all of these tasks just have to be done
within 10 days or something like that, and the order they
are completed doesn't matter? Or should I just schedule
them one after the other and when I actually complete
them I will update the ACTUAL dates? Thanks!!