linking tasks

L

Lynn

taskA is 20 days duration. taskB needs to start when taskA has run for
15days.

How do I link taskA to taskB ?

thanks
 
R

Rob Schneider

Lynn,

If I am interpreting you correctly, Task B would have Task A as a
predecessor with a SS link with +15 days of lag, which means that Task B
would start 15 days after the start of Task A.

--rms

www.rmschneider.com
 
S

Steve House

You could do it a couple of ways, depending on which actually best models
the actual physical process. If you mean Task B can start 15 days after
Task A starts, link A to B Start-to-Start and add a 15 day lag time. If you
mean Task B will be able to start 5 days before A ends, link A to B FS and
add a 5 day lead time. If you mean B should start when A is 3/4 done, link
A to B FS with a 25% lead time - in that case, if the duration of A changes,
the exact amount of overlap will adjust so that it will always be 25% of A's
duration, whatever it turns out to be.

Remember that links model physical requirments, not preferred time
relationships. It's not that you want B to start 15 days after A, it's that
A is producing something required by B and that something won't exist until
A has been running for a certain period of time or has reached a certain
level of completion. Also, the link doesn't specify when B WILL start, it
specifys the earliest time B will BE ABLE to start .... there's a
difference. Any number of other factors (like the only person who has the
skills to do B is on vacation the day when A gets to the point B can start,
for example) might make it actually start later than that no matter what the
link says.

HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top