Diana
How do I constrain Task 3 to start and finish as follows: Tasks 2 and 3 start
as soon as Task 1 is completed. Task 3 finishes 2 weeks after Task 2 is
completed.
I'm setting the predecessors for Task 3 as follow => 1,2FF+2 wks. Finish day
is calculated correctly but the start date moves to match the default
duration.
Thanks in advance,
Diana
as soon as Task 1 is completed. Task 3 finishes 2 weeks after Task 2 is
completed.
I'm setting the predecessors for Task 3 as follow => 1,2FF+2 wks. Finish day
is calculated correctly but the start date moves to match the default
duration.
Thanks in advance,
Diana