P
Paul Peterson - Velox Consulting, LLC
I am having a bizarre problem - I'm seeing this in all of our plans so I
created a new plan to test this out. This is what is happening. I created
two tasks - Task 1 has a Start Date of 10/13, and the duration is 2 days.
Task 2 is linked to Task 1 and has a duration of 5 days. Even though they
are linked, Task 2 has a start date of 10/13 - it should have a start date of
10/15. I have no constraints, and the type of relationship is FS. I am so
confused as I've never seen this before. Any help would be greatly
appreciated.
Paul C. Peterson.
created a new plan to test this out. This is what is happening. I created
two tasks - Task 1 has a Start Date of 10/13, and the duration is 2 days.
Task 2 is linked to Task 1 and has a duration of 5 days. Even though they
are linked, Task 2 has a start date of 10/13 - it should have a start date of
10/15. I have no constraints, and the type of relationship is FS. I am so
confused as I've never seen this before. Any help would be greatly
appreciated.
Paul C. Peterson.