B
Bernard
Hi,
In a project, I have 2 summary tasks, SUMMARY 1 and SUMMARY 2.
Each one contains subtasks.
I can see the Gant bars of the subtasks in the bars of the summary tasks,
even when the summary tasks are collapsed.
The problem :
If I link a subtask from SUMMARY 1 to a subtask in SUMMARY 2, I cannot see
the link between the reported gant bars of these subtasks when the two
summary tasks are collapsed.
Is there a way to see this link ?
(i.e. a way to see the link between the reported gant bar of the subtask1 in
the summary 1 and the reported gant bar of the subtask 2 in the summary 2).
I hope it's clear...
Any suggestion ?
Thank you in advance,
Bernard
In a project, I have 2 summary tasks, SUMMARY 1 and SUMMARY 2.
Each one contains subtasks.
I can see the Gant bars of the subtasks in the bars of the summary tasks,
even when the summary tasks are collapsed.
The problem :
If I link a subtask from SUMMARY 1 to a subtask in SUMMARY 2, I cannot see
the link between the reported gant bars of these subtasks when the two
summary tasks are collapsed.
Is there a way to see this link ?
(i.e. a way to see the link between the reported gant bar of the subtask1 in
the summary 1 and the reported gant bar of the subtask 2 in the summary 2).
I hope it's clear...
Any suggestion ?
Thank you in advance,
Bernard