Is there a way to preserve the link display between subtasks when they are rolled into a summary task? The links disappear when the sub-tasks are rolled up. A current project has many (430 or so) short duration sub-tasks which are linked to other subtasks in the same and other summary tasks. For clarity I would like to be able to display the sub-task link even after it's rolled up into a summary task. Filtering for "Critcal" yeilds about 150 disparate critical tasks which are difficult to decifer even on "D-size" printouts.