M
maryj
Using Project 2003. I added some tasks. In the Optimistic view, I've linked 2
tasks, Finish-to-Start, Start as soon as possible, yet the start date for the
2nd task does not change. When I switch to the standard Gantt chart, the
proper links are visible. Do those other views need to be refreshed in some
way?
Thanks!
tasks, Finish-to-Start, Start as soon as possible, yet the start date for the
2nd task does not change. When I switch to the standard Gantt chart, the
proper links are visible. Do those other views need to be refreshed in some
way?
Thanks!