J
Jimmy
I am importing task information into project. The information has
partially completed tasks so the records have values for task_act_work
and task_pct_work_comp. It does not seem to matter what I do - this
information displays incorrectly in Project. For example, the table
MSP_Tasks will have a value of 30 in task_pct_work_comp field for a
particular row but project will display that same row with a value of
zero. If I save the information in Project and then update the fields
for task_act_work and task_pct_work_comp the values will then display
correctly. But I cannot seem to get these values to display correctly
in Project when I first load the information. Any ideas? Thanks very
much for any info.
partially completed tasks so the records have values for task_act_work
and task_pct_work_comp. It does not seem to matter what I do - this
information displays incorrectly in Project. For example, the table
MSP_Tasks will have a value of 30 in task_pct_work_comp field for a
particular row but project will display that same row with a value of
zero. If I save the information in Project and then update the fields
for task_act_work and task_pct_work_comp the values will then display
correctly. But I cannot seem to get these values to display correctly
in Project when I first load the information. Any ideas? Thanks very
much for any info.