Loading grid in task updates

C

Clarion

I am not able to approve the tasks for a specific project (Both in PWA and
Pro2007). Can anyone help me?
 
A

Andrew Lavinsky

Check to see if you are the status manager on the tasks in the project plan:
Open the plan, display the Status Manager field, confirm your name is in it.
If not, change to your name, save and publish.
 