M
Matteo
Dear all,
sometime I am facing with some PM that create his project outside the
headquarter, (not connected to the server, with don't have a vpn connecting
to our project server, nor is installed in our DMZ) and importing it into an
Enterprise project he/she see dates chaging because the enterpise calendar
that includes holidays.
The question is:
Is there a way to export the enterprise calendar and generate a local
calendar from this export, for all the client?
Is it available a tool to propagate this calendar to all project
professional 2007 installation?
Thank you all
Matteo
sometime I am facing with some PM that create his project outside the
headquarter, (not connected to the server, with don't have a vpn connecting
to our project server, nor is installed in our DMZ) and importing it into an
Enterprise project he/she see dates chaging because the enterpise calendar
that includes holidays.
The question is:
Is there a way to export the enterprise calendar and generate a local
calendar from this export, for all the client?
Is it available a tool to propagate this calendar to all project
professional 2007 installation?
Thank you all
Matteo