Hi Listers
I am using project Server 2003.
We have a requirement where we need to "de-activate" few Task outline
codes.
This means that the historical tasks should still have that outline
code value ,
but all new tasks should not be able to select the "de-activated"
outline code.
So far as I have seen in Project I don't think this could be done.
Did anybody else face this issue ? How did you resolve this.
Only way to do this which I can think of is to write - Deleted after
the outline code
value and hope that people don't choose that value.
Thanks a lot in advance ...
Rajan
I am using project Server 2003.
We have a requirement where we need to "de-activate" few Task outline
codes.
This means that the historical tasks should still have that outline
code value ,
but all new tasks should not be able to select the "de-activated"
outline code.
So far as I have seen in Project I don't think this could be done.
Did anybody else face this issue ? How did you resolve this.
Only way to do this which I can think of is to write - Deleted after
the outline code
value and hope that people don't choose that value.
Thanks a lot in advance ...
Rajan