Locking Timesheet for Non Managed Period

S

Sneha Satish

Hi All,

My organization has successfully implemented EPM 2003. We extract the actual
hours spent by each resource by project for the sake of billing every month.

I have a clarification. After the resources have entered their respective
actual hours spent on the tasks assigned to them, I need to lock the
timesheet for the entire month. Currently we are using the non managed period
option.

Can you pls suggest a remedy for locking timesheet for non managed period?
 
J

JulieS

Hello Sneha Satish,

As your question concerns Project Server I suggest you re-post your
question to the project server newsgroup
(microsoft.public.project.server) if you haven't already posted there.

Although most of the folks who answer questions in the newsgroups visit
all the groups, I think you'll find there's a higher concentration of
"server gurus" in the server newsgroup and you may get a quicker answer.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 