H
hammondrob1
Hi all. Recently I had a discussion with a project manager who was
adamant that applying logic to summary tasks was acceptable and
allowed him to build his schedule from the top down. I raised the
fact that there was an implicit assumption that all tasks contained
under the first summary bar must be completed before any task under
the susbsequent summary bar could commence (ie highly sequential work
when the real world often allows work to be done in parallel). He did
counter that with the status overiding logic option switched on he
could remove the pessimistic forecast that might otherwise be produced
from sequential rather than parallel tasks. I was a loss to explain
any other good reason for not applying logic to summary tasks apart
from being 'good practice'.
Has anyone got any suggestions why logic on summary tasks is not
encouraged? (Using MSp2003 SP3 standalone in master child
structure). Thanks
adamant that applying logic to summary tasks was acceptable and
allowed him to build his schedule from the top down. I raised the
fact that there was an implicit assumption that all tasks contained
under the first summary bar must be completed before any task under
the susbsequent summary bar could commence (ie highly sequential work
when the real world often allows work to be done in parallel). He did
counter that with the status overiding logic option switched on he
could remove the pessimistic forecast that might otherwise be produced
from sequential rather than parallel tasks. I was a loss to explain
any other good reason for not applying logic to summary tasks apart
from being 'good practice'.
Has anyone got any suggestions why logic on summary tasks is not
encouraged? (Using MSp2003 SP3 standalone in master child
structure). Thanks