Hi,
I have problem with one Project. It take ageto publish it. I checked other
projects and publishing is quite fast.
I was trying to investigate that case but in the log I can see plenty of
that errors:
---------------------
06/24/2009 12:52:01.05 Microsoft.Office.Project.Server
(0x17E0) 0x29EC Project Server Project Server-side Project
Ope 76yg Assert some big time error StackTrace: at
Microsoft.Office.Project.DataEdit.Tasks.TaskCntr.RecomputeAssnDates(TaskNode
taskNode) at
Microsoft.Office.Project.DataEdit.Assignments.AssnCntr.SetPeriodActualWork(AssnNode
assnNode, TaskNode taskNode, DateTime dtStart, DateTime dtEnd, Double wrk,
Boolean fRollup) at
Microsoft.Office.Project.DataEdit.Assignments.AssnCntr.SetPeriodAssnActualWork(Guid
guid, DateTime dtStart, DateTime dtEnd, Double wrk, Boolean fRollup) at
Microsoft.Office.Project.DataEdit.Obj.ProjCntr.SetPeriodData(Guid guid,
UInt32 pid, DateTime dtStart, DateTime dtEnd, Object obj, Boolean fRollup,
Boolean fDisableSlowTaskRecompution) at
Microsoft.Office.Project.DataEdit.Document.SvrDoc.SetPeriodData(Int32
entityID, Guid guid, UInt32 propertyID, DateTime dtStart,
DateTim... baee0256-bc23-4543-944f-7ce7ea29c008
-------------------
Could you please help and solve taht mistry.
I checked the project and seems to be "configured" correctly.
We have PWA 2007 SP1 with December Cumulative update.
Project Managers use Project Pro 2007 SP1.
We have different servers with different roles as SQL, PWA, Sharepoint.
Thank you for help.
I have problem with one Project. It take ageto publish it. I checked other
projects and publishing is quite fast.
I was trying to investigate that case but in the log I can see plenty of
that errors:
---------------------
06/24/2009 12:52:01.05 Microsoft.Office.Project.Server
(0x17E0) 0x29EC Project Server Project Server-side Project
Ope 76yg Assert some big time error StackTrace: at
Microsoft.Office.Project.DataEdit.Tasks.TaskCntr.RecomputeAssnDates(TaskNode
taskNode) at
Microsoft.Office.Project.DataEdit.Assignments.AssnCntr.SetPeriodActualWork(AssnNode
assnNode, TaskNode taskNode, DateTime dtStart, DateTime dtEnd, Double wrk,
Boolean fRollup) at
Microsoft.Office.Project.DataEdit.Assignments.AssnCntr.SetPeriodAssnActualWork(Guid
guid, DateTime dtStart, DateTime dtEnd, Double wrk, Boolean fRollup) at
Microsoft.Office.Project.DataEdit.Obj.ProjCntr.SetPeriodData(Guid guid,
UInt32 pid, DateTime dtStart, DateTime dtEnd, Object obj, Boolean fRollup,
Boolean fDisableSlowTaskRecompution) at
Microsoft.Office.Project.DataEdit.Document.SvrDoc.SetPeriodData(Int32
entityID, Guid guid, UInt32 propertyID, DateTime dtStart,
DateTim... baee0256-bc23-4543-944f-7ce7ea29c008
-------------------
Could you please help and solve taht mistry.
I checked the project and seems to be "configured" correctly.
We have PWA 2007 SP1 with December Cumulative update.
Project Managers use Project Pro 2007 SP1.
We have different servers with different roles as SQL, PWA, Sharepoint.
Thank you for help.