I need to turn in regularly metrics numbers on a master integrated schedule.
I am using Project 2003, but getting ready to switch to 2007. I need the
number of actual real tasks (non-LOE, non-summary) that start/finish on time
Vs. late numbers. I usually run reports of actual starts/finish’s Vs. the
Baseline starts/finish’s, then copy and past those columns into Excel to do
the counting for me. I have been told there are some tools that could help
automate the process, but I cannot find anything on the web that does what I
am looking for. Someone mentioned something called RoboCount, but again I
cannot find anything on the web about it.
I would appreciate any information anyone has that could help me out.
Thanks, Doug
I am using Project 2003, but getting ready to switch to 2007. I need the
number of actual real tasks (non-LOE, non-summary) that start/finish on time
Vs. late numbers. I usually run reports of actual starts/finish’s Vs. the
Baseline starts/finish’s, then copy and past those columns into Excel to do
the counting for me. I have been told there are some tools that could help
automate the process, but I cannot find anything on the web that does what I
am looking for. Someone mentioned something called RoboCount, but again I
cannot find anything on the web about it.
I would appreciate any information anyone has that could help me out.