Looking for advise about over budgeted hours

C

chris

HI
I'm using microsoft project 98 for the first time, i know
what i want to do but can't find the columns to achieve it.
This is what i want to project to show

Budgeted work TIME SPENT TO DATE %COMPLETE
100HOURS 150HOURS 50

then in another colums i want project to forcast that the
total number of hours would now come to 300.

I hope someone can give me a hand, if not then could
someone point me in the right direction for some advise

thanks
 
J

Jan De Messemaeker

Hi Chris,

1. Budgeted hours. These are called Baseline Work, and to populate it, you
have to save a baseline for the project at the onset ;

2. Time spent to-date is called Actual Work

3. % Complete is called % complete

4. Total Work is called Work.

5. One youy didn't ask, but comes in handy, is Remaining Work (much better
to record progress than % complete, let Project do the % calculation!)

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 