C
chris
HI
I'm using microsoft project 98 for the first time, i know
what i want to do but can't find the columns to achieve it.
This is what i want to project to show
Budgeted work TIME SPENT TO DATE %COMPLETE
100HOURS 150HOURS 50
then in another colums i want project to forcast that the
total number of hours would now come to 300.
I hope someone can give me a hand, if not then could
someone point me in the right direction for some advise
thanks
I'm using microsoft project 98 for the first time, i know
what i want to do but can't find the columns to achieve it.
This is what i want to project to show
Budgeted work TIME SPENT TO DATE %COMPLETE
100HOURS 150HOURS 50
then in another colums i want project to forcast that the
total number of hours would now come to 300.
I hope someone can give me a hand, if not then could
someone point me in the right direction for some advise
thanks