A
AA
Hi All,
I am currently modifying the tasks in Project Server via SQL invoking
MSP_BACKUP_TASK as described in the Microsoft Documentation. All seems to go
fine.
However, if the regional settings are changed to UK from US the actuals are
lost. Seems to be a bug in MS PROJECT (2002 and 2003 also). IF i change the
calculation to manual, then i see the proper values of actuals.
Anyone experienced this before or has any idea?
regards.
I am currently modifying the tasks in Project Server via SQL invoking
MSP_BACKUP_TASK as described in the Microsoft Documentation. All seems to go
fine.
However, if the regional settings are changed to UK from US the actuals are
lost. Seems to be a bug in MS PROJECT (2002 and 2003 also). IF i change the
calculation to manual, then i see the proper values of actuals.
Anyone experienced this before or has any idea?
regards.