Kristi F
Kristi F wrote:
I am using Web Access to track the progress of my project. The
tracking option used is: "Always track by entering the hours of work
done per time period" - which provides the timesheet view. However,
for some reason, when I accept the updates, they aren't actually
showing up in my project for each of them. Is this because my tasks
are fixed work and there are entering over and above the inital
planned work time? Should I be using another 'Task Type' so that the
plan is flexible enough to allow for these updates?
I am using Web Access to track the progress of my project. The
tracking option used is: "Always track by entering the hours of work
done per time period" - which provides the timesheet view. However,
for some reason, when I accept the updates, they aren't actually
showing up in my project for each of them. Is this because my tasks
are fixed work and there are entering over and above the inital
planned work time? Should I be using another 'Task Type' so that the
plan is flexible enough to allow for these updates?