Hi Steve,
I don't understand completely what you are saying, so let me try to
re-state what I think is happening and see if we can't get this
sorted.
I am guessing you are changing a resource's working calendar by
either adding non-working time or modifying the working hours on
specific days and you are seeing resource overallocations (redline)
disappear. Is that correct?
Changing a resource's calendar will alter when work is scheduled
however, I can't come up with a scenario where changing a resource's
calendar will resolve resource overallocations.
Can you give a bit more detail about what specifically is happening.
Also please include what version of Project (2000, 2003, 2007) you
are using plus service pack information.
I hope this helps. Let us know how you get along.
Julie
Project MVP