Losing Resource OverAllocations in Resource Sheet (Redlined)

S

Steve

When I post a resource calendar update to the resource sheet, my redline at
the resource level on the resource sheet is turning off - why? How do I
prevent this?

I am manually resource leveing and not leveling at this time.
 
J

JulieS

Hi Steve,

I don't understand completely what you are saying, so let me try to
re-state what I think is happening and see if we can't get this
sorted.

I am guessing you are changing a resource's working calendar by
either adding non-working time or modifying the working hours on
specific days and you are seeing resource overallocations (redline)
disappear. Is that correct?

Changing a resource's calendar will alter when work is scheduled
however, I can't come up with a scenario where changing a resource's
calendar will resolve resource overallocations.

Can you give a bit more detail about what specifically is happening.
Also please include what version of Project (2000, 2003, 2007) you
are using plus service pack information.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top