Robin
We are using MSP 2003 with Project Web Access. We download reports from
Resources/View Resource Assignments/summary view, timesheet view showing
actual time, overtime by week from Jan1 to the present. People enter time in
PWA, approve and update to MSP daily. We ran reports at the end of June and
again at the end of July and show hours missing for some people. The earlier
report showed 50+ hours the week of 5/11 for one person, but only 9.75 for
the same week on the later report. I am showing all projects, not just
current projects. We figured out what project should have had the hours for
that week, found them in MSP, republished and got most of them back. However
this is not the only person and week this has happened to and with over 600
projects, I can't go in and republish each and hope the hours reappear. Has
any one heard of this or do you have any ideas what the root cause may be?
Resources/View Resource Assignments/summary view, timesheet view showing
actual time, overtime by week from Jan1 to the present. People enter time in
PWA, approve and update to MSP daily. We ran reports at the end of June and
again at the end of July and show hours missing for some people. The earlier
report showed 50+ hours the week of 5/11 for one person, but only 9.75 for
the same week on the later report. I am showing all projects, not just
current projects. We figured out what project should have had the hours for
that week, found them in MSP, republished and got most of them back. However
this is not the only person and week this has happened to and with over 600
projects, I can't go in and republish each and hope the hours reappear. Has
any one heard of this or do you have any ideas what the root cause may be?