P
paul.burton
Hi,
I'm using MPSE 2007 all relevant service packs installed.
I have a large programme with multiple layers of management who wish
to track milestones they are accountable for.
We have smaller work package and project teams creating schedules.
These contain consistent milestones cascaded from the customer down
through the programme levels for teams to deliver and work package,
project and programme managers to track.
For corporate reasons we there has been pressure to avoid using master
projects so "summary schedules" have been created for managers to
track milestones. As the work to reach the milestones is done by their
teams, and should be updated in their schedules, it is a waste to
manually update 3 or 4 levels of schedule with the same information,
i.e. "X" milestone 100% complete.
Understanding the issues in dynamic linking of cells between projects
I thought I had got around this by linking tasks using cross project
task links and then OLE linking the "actual finish" cell from the
resulting predecessor "ghost task".
This seems a natural solution as the ghost task creates a line item in
the schedule and should therefore work as an internal OLE link (which
the system seems to manage quite well), and indeed works well.
The problem is that if you then insert the file into a consolidated
project to create more cross project links, or import a file as a
subproject to make these links the "internal" OLE links that have
already been created fail the next time the file is opened. In a
rolling wave environment it is difficult to avoid needing to update
cross project links.
Any advice would be appreciated...
Thanks,
Paul
I'm using MPSE 2007 all relevant service packs installed.
I have a large programme with multiple layers of management who wish
to track milestones they are accountable for.
We have smaller work package and project teams creating schedules.
These contain consistent milestones cascaded from the customer down
through the programme levels for teams to deliver and work package,
project and programme managers to track.
For corporate reasons we there has been pressure to avoid using master
projects so "summary schedules" have been created for managers to
track milestones. As the work to reach the milestones is done by their
teams, and should be updated in their schedules, it is a waste to
manually update 3 or 4 levels of schedule with the same information,
i.e. "X" milestone 100% complete.
Understanding the issues in dynamic linking of cells between projects
I thought I had got around this by linking tasks using cross project
task links and then OLE linking the "actual finish" cell from the
resulting predecessor "ghost task".
This seems a natural solution as the ghost task creates a line item in
the schedule and should therefore work as an internal OLE link (which
the system seems to manage quite well), and indeed works well.
The problem is that if you then insert the file into a consolidated
project to create more cross project links, or import a file as a
subproject to make these links the "internal" OLE links that have
already been created fail the next time the file is opened. In a
rolling wave environment it is difficult to avoid needing to update
cross project links.
Any advice would be appreciated...
Thanks,
Paul