S
Scott K. Mitchell
Anyone out there have a macro that will automatically assign the remaining
availability for a resource to a task for a given duration?
For example:
Name Start Finish Work Resource
Task 1 1/1/02 1/3/02 2d Bob[67%]
Task 2 1/4/02 1/6/02 1d Bob[33%]
Task 3 1/1/02 1/6/02 ?? Bob[???]
I want a macro that automatically takes Bob's remaining availability for the
period between 1/1/02 and 1/6/02, and puts that as the timephased work for
task 3. If you have one, please share!
Thanks in advance for any help,
Scott
availability for a resource to a task for a given duration?
For example:
Name Start Finish Work Resource
Task 1 1/1/02 1/3/02 2d Bob[67%]
Task 2 1/4/02 1/6/02 1d Bob[33%]
Task 3 1/1/02 1/6/02 ?? Bob[???]
I want a macro that automatically takes Bob's remaining availability for the
period between 1/1/02 and 1/6/02, and puts that as the timephased work for
task 3. If you have one, please share!
Thanks in advance for any help,
Scott