Main task %completion not getting updated based on subtask-value

M

Mangal Baikar

am facing some strange issue in MS project. After updating the % completion
for any subtask, it is not getting reflected for main task. Because of this
the project % of completion value is always shown very less. This was not
happening earlier.

If I open same file on any other machine the values get auto updated. I
tried reinstalling the software.
MS Project Professional 2003 SP2

Please let me know if any one knows the solution for the same
 
C

Catfish Hunter

There are several percent's in Projects. The one that does not update the
resource is Percent of Work. Make sure you are useing % Complete.
 
C

Catfish Hunter

Did you look at your calculation setting to make sure it was set to Auto?
(Tools>Options>Calculation)
 
M

Mangal Baikar

It worked.... thanks a lot

Mangal

Catfish Hunter said:
Did you look at your calculation setting to make sure it was set to Auto?
(Tools>Options>Calculation)
 