I
Irish Gues
Hi, we currently have a Microsoft Project Server 2003 install running. We are
struggling with how to deal with maintenance activities within the
department. We have about 100 different systems that we maintain and we want
to be able to track the time spent on each system. Are there any best
practices out there for this? Currently, we have a project plan with a task
line for each system and the appropriate resource assigned to each task. The
work effort is estimated and spread out evenly over the fiscal year. Of
course, as soon as anyone puts any time against it, Project recalculates the
duration and/or effort and it requires a lot of upkeep. We toyed with an
administrative project, but are not sure that is the way to go. Any advice
would be appreciated!
struggling with how to deal with maintenance activities within the
department. We have about 100 different systems that we maintain and we want
to be able to track the time spent on each system. Are there any best
practices out there for this? Currently, we have a project plan with a task
line for each system and the appropriate resource assigned to each task. The
work effort is estimated and spread out evenly over the fiscal year. Of
course, as soon as anyone puts any time against it, Project recalculates the
duration and/or effort and it requires a lot of upkeep. We toyed with an
administrative project, but are not sure that is the way to go. Any advice
would be appreciated!