T
Thomas Czichowsky
Hi all,
I'm using Project Server 2002 and am dealing with an issue regarding
unfinished tasks. I don't want resources to update actuals on a task
if the finish date lies a certain period of time in the past. For
example: A task should have been finished 4 months ago but is not yet
finished. In this case it should not be possible for a team member to
assign actual work to this task.
I first thought of filtering the timesheet view but found no
possibility how to do this. It is also not possible to delete these
tasks or assignements since I want to keep this information.
I'm thankful for any ideas on this issue!
Regards Thomas
I'm using Project Server 2002 and am dealing with an issue regarding
unfinished tasks. I don't want resources to update actuals on a task
if the finish date lies a certain period of time in the past. For
example: A task should have been finished 4 months ago but is not yet
finished. In this case it should not be possible for a team member to
assign actual work to this task.
I first thought of filtering the timesheet view but found no
possibility how to do this. It is also not possible to delete these
tasks or assignements since I want to keep this information.
I'm thankful for any ideas on this issue!
Regards Thomas