Hi There,
I'm not sure if this can be done but if it can it will be very useful for us.
I have added a Custom Enterprise Field (Task - Enterprise Number 1) called
Project Number.
It appears as it should in the Enterprise Gant Sheet in Project Pro and I am
able to add the project number to it.
My problem is that I am unable to display this column in the Resource Usge
sheet where I need to export some information from.
The "Project Number" field just doesnt appear in the list of fields to
select from.
Can someone help me out, we are desperate to get this field in both places.
Thanks in advance
Ris
I'm not sure if this can be done but if it can it will be very useful for us.
I have added a Custom Enterprise Field (Task - Enterprise Number 1) called
Project Number.
It appears as it should in the Enterprise Gant Sheet in Project Pro and I am
able to add the project number to it.
My problem is that I am unable to display this column in the Resource Usge
sheet where I need to export some information from.
The "Project Number" field just doesnt appear in the list of fields to
select from.
Can someone help me out, we are desperate to get this field in both places.
Thanks in advance