How can you put a task into your project that has no time value, but
has a dependency relationship with other tasks; for example, waiting
for the receipt of data from an outside office. In a project putting
in "0" days makes that task a milestone, and I certainly don't want
that either.
thanks.
Naomi
has a dependency relationship with other tasks; for example, waiting
for the receipt of data from an outside office. In a project putting
in "0" days makes that task a milestone, and I certainly don't want
that either.
thanks.
Naomi