Making changes to Resource Pool work units and copying existing ta

J

Jude

I have been made aware that not putting resources in as 100% work units in my
Resource Pool has caused over allocation issues due to the differences
between the % work and the project calendar and durations etc. So what is the
best way of making the necessary changes?

Do I need to make changes to the Resource Pool first and then copy the tasks
into a new project? If so, how do I ensure that the start dates set by
project in my current project, do not become constraints when they are copied
in to the replacement project?

Any ideas welcome!

Thanks
Jude
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top