I have been made aware that not putting resources in as 100% work units in my
Resource Pool has caused over allocation issues due to the differences
between the % work and the project calendar and durations etc. So what is the
best way of making the necessary changes?
Do I need to make changes to the Resource Pool first and then copy the tasks
into a new project? If so, how do I ensure that the start dates set by
project in my current project, do not become constraints when they are copied
in to the replacement project?
Any ideas welcome!
Thanks
Jude
Resource Pool has caused over allocation issues due to the differences
between the % work and the project calendar and durations etc. So what is the
best way of making the necessary changes?
Do I need to make changes to the Resource Pool first and then copy the tasks
into a new project? If so, how do I ensure that the start dates set by
project in my current project, do not become constraints when they are copied
in to the replacement project?
Any ideas welcome!
Thanks
Jude