It will calculate the work for a task in man-hours if you input the expected
duration of the task, the hours per day the resources works (his calendar),
and the percentage of his working time you expect him to devote to the task.
Joe works M-F 8-5 with an hour for lunch. He is assigned 100% to a task
with an expected duration of 5 days. Project will calculate that the task
will require 40 man-hours of work to complete.