R
Robert E Jones III
The resource pool here is unique to say the least.
Since Project Server 2003 and EPK are installed and used the company still
struggles with Man loading.
I have suggested using Resource Calendars as a means to so show non working
times for staff, but that went through one ear and out the other.
In a meeting this week someone suggested using the % availability as a means
to resolve the allocation issues.
Example Joe is allocated to work 50% of his time on Project X and 50% of his
time on Project Z and not used anywhere else.
So I guess we are saying when a resource is loaded onto a project the
availability is loaded at 50% for each project for that resource?
I have never seen it done this way?
Since Project Server 2003 and EPK are installed and used the company still
struggles with Man loading.
I have suggested using Resource Calendars as a means to so show non working
times for staff, but that went through one ear and out the other.
In a meeting this week someone suggested using the % availability as a means
to resolve the allocation issues.
Example Joe is allocated to work 50% of his time on Project X and 50% of his
time on Project Z and not used anywhere else.
So I guess we are saying when a resource is loaded onto a project the
availability is loaded at 50% for each project for that resource?
I have never seen it done this way?