Y
Yves
I have to manage actual time for a group of resources. One entry each week
for the group. I do not want to use a Project Server Authentification. WE
use Project 2003 and managed periods method. The above solution didn't work,
because it's impossible to enter actual hours in a Project plan using managed
periods. When I do that, the synchronisation process start and delete
automatically all the data already entered.
Do you have other solution, please,
1. Ask your Project Server to create a Generic resource in the Enterprise
Resource Pool representing this group of people
2. In the Microsoft Project plan, assign the Generic resource to the tasks
on which the group of people will work
3. Enter actuals for the group in the Microsoft Project plan each week
This didn't work.
Thanks
Yves
for the group. I do not want to use a Project Server Authentification. WE
use Project 2003 and managed periods method. The above solution didn't work,
because it's impossible to enter actual hours in a Project plan using managed
periods. When I do that, the synchronisation process start and delete
automatically all the data already entered.
Do you have other solution, please,
1. Ask your Project Server to create a Generic resource in the Enterprise
Resource Pool representing this group of people
2. In the Microsoft Project plan, assign the Generic resource to the tasks
on which the group of people will work
3. Enter actuals for the group in the Microsoft Project plan each week
This didn't work.
Thanks
Yves