Hello,

At Manage Queue Jobs screen. at Job state column I see "Skipped For
Optimization".

What is this field about ?

Regards

Pearl
 
G

Gary L. Chefetz [MVP]

Perl:

The Queue service actually optimizes the job stream by skipping redundant
jobs. For instance, if a PM, in short order, saves, publishes, saves again,
and publishes again, the system will execute the two save operations and
execute only the last publish request to save processing time.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 
G

GM

That makes sense, but in the case of processing a single task update (an
"accepted" task) would it skip for optimization?
Thanks
 