Using MSProject2003ent

I have created a view (type Project) that basically lists all resources per
task. Is there a way to setup the view so each task is out dented and the
list of resources under each task are indented? It does list the information
correctly but indenting would make it more pleasing to the eyes. (Plus it
will be easier for others to desirer)
 
D

Dale Howard [MVP]

Reuter --

Unfortunately, the answer to your question is "No." The goal would be to
create a View in PWA that is similar to the Task Usage view in Project
Professional 2007. I tried to create a Project view based on the Assignment
table using grouping, but that simply does not work as desired. Sorry.
Hope this helps.
 