A
Andrea
I am having a major quagmire. This client is tracking
hours in some project plans and % complete in others. The
default in PWA is set at % complete and then the plans
tracking hours are being changed through Proj Pro(
Tools>Customize>Published Field> Always Use A Specific
Method of Progress> Hours of Work Done per Time Period.
They are trying to approve timesheets, however, a message
is being received staying that we need Project Pro 2003 to
perform this action along with some additional verbage
about the server admin checking the Project Server Account
set up, etc. Ok--then we go and check the Global
Permissions on the Server Configuration page of PWA and
verify that the permissions for timesheet approval are set
to "allow"---then we go to save the changes and we get
another message--which states the " YOU CANNOT TURN ON
TIMESHEET APPROVAL UNLESS YOUR TIME PERIOD IS SET TO
MANAGED PERIODS. TO DO THIS GO TO THE ADMIN CENTER AND
CLICK CUSTOMIZE PWA".
Well---I can't use Managed Periods because then I lose the
option to choose a different tracking setting for
reporting progress on tasks --and locks down the default
to force managers to use the default reporting method only.
Ok--did I lose you, confuse you, or both. ( Thank you
in advance!!!!
Regards,
Anxious Andrea
hours in some project plans and % complete in others. The
default in PWA is set at % complete and then the plans
tracking hours are being changed through Proj Pro(
Tools>Customize>Published Field> Always Use A Specific
Method of Progress> Hours of Work Done per Time Period.
They are trying to approve timesheets, however, a message
is being received staying that we need Project Pro 2003 to
perform this action along with some additional verbage
about the server admin checking the Project Server Account
set up, etc. Ok--then we go and check the Global
Permissions on the Server Configuration page of PWA and
verify that the permissions for timesheet approval are set
to "allow"---then we go to save the changes and we get
another message--which states the " YOU CANNOT TURN ON
TIMESHEET APPROVAL UNLESS YOUR TIME PERIOD IS SET TO
MANAGED PERIODS. TO DO THIS GO TO THE ADMIN CENTER AND
CLICK CUSTOMIZE PWA".
Well---I can't use Managed Periods because then I lose the
option to choose a different tracking setting for
reporting progress on tasks --and locks down the default
to force managers to use the default reporting method only.
Ok--did I lose you, confuse you, or both. ( Thank you
in advance!!!!
Regards,
Anxious Andrea