V
V
1) If the resource forgets to enter the time for that
week and that time period is closed, how do we capture
the actuals?
Resetting the managed time period as open and requesting
the individual to resubmit the time may not be practical
because of organization's size. Can the project manager
directly enter time into professional if managed time
period is enabled?
2) Is there a way to know which resources have submitted
their time for that given week. Is there a standard
report that answers this question?
Appreciate your insights.
Thanks,
V
week and that time period is closed, how do we capture
the actuals?
Resetting the managed time period as open and requesting
the individual to resubmit the time may not be practical
because of organization's size. Can the project manager
directly enter time into professional if managed time
period is enabled?
2) Is there a way to know which resources have submitted
their time for that given week. Is there a standard
report that answers this question?
Appreciate your insights.
Thanks,
V