R
Reuter
Using MSProject2003ent "I know"
Original PWA settings were for Non-Managed time periods (fiscal year - first
Sunday in October), but because we link to SAP and SAP is a week behind
MSProject (SAP Fiscal year- 2nd week in October) they didn't line up under
(Tasks/Timesheet view). After configuring PWA to utilize (Managed Time
periods) lining them up with SAP the users started seeing their Actuals
disappearing. Any idea on why this is accruing and how to resolve the issue
while still using Managed time periods?
Original PWA settings were for Non-Managed time periods (fiscal year - first
Sunday in October), but because we link to SAP and SAP is a week behind
MSProject (SAP Fiscal year- 2nd week in October) they didn't line up under
(Tasks/Timesheet view). After configuring PWA to utilize (Managed Time
periods) lining them up with SAP the users started seeing their Actuals
disappearing. Any idea on why this is accruing and how to resolve the issue
while still using Managed time periods?