Managed Time Periods

B

Barbara G

Hi,
Our timesheets start on Monday however the projects and Data Analysis
displays Sunday as the day when actual work is recorded. I have a user who
worked overtime on Sunday and then worked her normal shift starting Monday.
When I look in Data Analysis, it only displays the actual work on Sunday. Is
there a way to change the day of the week the timesheet starts on to Sunday
so it matches the cube and the project? Any suggestions would be greatly
appreciated. Thanks.
 
J

Jesse Schuchart, MCITP - EPM, MCT

Open Project Web Access
Click on Server Settings
Click on Timesheet Periods

If the days in the time sheet periods are set and start on Mondays, then I
would leave them, as deleting them and recreating them can cause harm to past
reported timesheets and entries.

Instead, I would update the Project Cube and rebuild it (Server Settings,
then Build Settings).
 
B

Barbara G

Hi Jesse,
Thank you for your help. How do you change the cube to show the start day
for the week from Sunday to Monday?

Thanks,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top