K
Katie B
Good morning,
In doing some research on the topic of timesheet approval and it's
connection to the layout of the RBS, I was able to determine that a
manager or lead approves anyone that falls below him/her in the RBS
outline code. However if the layout is as follows...
Manager A
-->Team 1 Lead
------>Team 1 Member A
------>Team 1 Member B
-->Team 2 Lead
------>Team 2 Member A
------>Team 2 Member B
Is it possible for Manager A to approve timesheets for the resources
that fall only one level beneath them (i.e Team 1 and Team 2 Leads)?
Or do they automatically see everyone including Team Leads and Team
Members?
The problem I'm having is just that: the manager on our project wants
to be able to approve timesheets for JUST the main team leads and not
everyone else that falls below that?
Is there any way that this is possible in either the structure of the
RBS or as a setting in PWA??
Please let me know. Your help is greatly appreciated!
Thanks!
Katie Begell
In doing some research on the topic of timesheet approval and it's
connection to the layout of the RBS, I was able to determine that a
manager or lead approves anyone that falls below him/her in the RBS
outline code. However if the layout is as follows...
Manager A
-->Team 1 Lead
------>Team 1 Member A
------>Team 1 Member B
-->Team 2 Lead
------>Team 2 Member A
------>Team 2 Member B
Is it possible for Manager A to approve timesheets for the resources
that fall only one level beneath them (i.e Team 1 and Team 2 Leads)?
Or do they automatically see everyone including Team Leads and Team
Members?
The problem I'm having is just that: the manager on our project wants
to be able to approve timesheets for JUST the main team leads and not
everyone else that falls below that?
Is there any way that this is possible in either the structure of the
RBS or as a setting in PWA??
Please let me know. Your help is greatly appreciated!
Thanks!
Katie Begell