kinetix
I'm working on a complex Federal design/build construction project tha
requires owner review of multiple design packages prior to start o
construction. The entire construction schedule is dependent on thei
review and authorization to proceed. The original schedule included tim
for that review, but they are quickly falling behind and can't/won'
provide a projected remaining duration or completion dates. Once th
reviews have actually been completed, I can update the actual finis
dates, but until that point I need a clean way to reflect the delays t
keep the rest of the schedule from just slipping into the past. The wa
I've come up with is to use a leveling delay on the successor task
which then zeros out when I enter actual dates. Any ideas. thank
requires owner review of multiple design packages prior to start o
construction. The entire construction schedule is dependent on thei
review and authorization to proceed. The original schedule included tim
for that review, but they are quickly falling behind and can't/won'
provide a projected remaining duration or completion dates. Once th
reviews have actually been completed, I can update the actual finis
dates, but until that point I need a clean way to reflect the delays t
keep the rest of the schedule from just slipping into the past. The wa
I've come up with is to use a leveling delay on the successor task
which then zeros out when I enter actual dates. Any ideas. thank