D
Dave Barr
I am program manager for a technical project where there are project
schedules for different groups (engineering, test, support, marketing etc).
I want to find the best way to get a single project where I can have
dependencies that are shared between each of the groups. I also want the
individual groups to be able to update their task lists.
Currently the 2 ways I can see to do this are:
1) Have a single schedule where I copy paste each groups tasks into and
indent. Then whenever they want to make changes to their schedules they
would edit the overall project file
2) Have a master schedule with individual schedules inserted. Then have the
groups update their individual schedules and have that roll into the master
schedule.
Option 2 sounds like the best way to do this as I like having the ability to
have individual schedules managed by the group leads. But I am having
difficulties finding the best way to manage dependencies between the
schedules. Ideally I'd like to open the master schedule and simply put a
dependency in one of the expanded inserted projects that relates to a task
in another expanded inserted project using the task number in the master
schedule but that doesn't work because when you open up the individually
inserted schedule it has it's own task numbers and not those in line with
the master schedule.
The only other way I can think to do this is to manually insert external
dependencies between each indivudual schedule by opening the schedule,
locating it's task number and then inserting the projname\taskid in the
other schedule. But I think this will be time consuming and prone to errors.
Does anybody out there know of a better way to do this?
Thanks for any help,
Dave
schedules for different groups (engineering, test, support, marketing etc).
I want to find the best way to get a single project where I can have
dependencies that are shared between each of the groups. I also want the
individual groups to be able to update their task lists.
Currently the 2 ways I can see to do this are:
1) Have a single schedule where I copy paste each groups tasks into and
indent. Then whenever they want to make changes to their schedules they
would edit the overall project file
2) Have a master schedule with individual schedules inserted. Then have the
groups update their individual schedules and have that roll into the master
schedule.
Option 2 sounds like the best way to do this as I like having the ability to
have individual schedules managed by the group leads. But I am having
difficulties finding the best way to manage dependencies between the
schedules. Ideally I'd like to open the master schedule and simply put a
dependency in one of the expanded inserted projects that relates to a task
in another expanded inserted project using the task number in the master
schedule but that doesn't work because when you open up the individually
inserted schedule it has it's own task numbers and not those in line with
the master schedule.
The only other way I can think to do this is to manually insert external
dependencies between each indivudual schedule by opening the schedule,
locating it's task number and then inserting the projname\taskid in the
other schedule. But I think this will be time consuming and prone to errors.
Does anybody out there know of a better way to do this?
Thanks for any help,
Dave