Hi,
I just recently upgraded towards MSP Server 2003. I get
stuck now on working with administrative / non-working
time. This option seems not to be available. The
following message occurs when using "Notify your manager
of time you will not be available for project work":
======================================================
You are not assigned to any tasks on any administrative
project, such as vacation, sick, or bereavement.
To submit time against an administrative project, you
must be assigned to a task on that project for the time
period that you are unavailable for project work.
Contact your server administrator if you feel you have
received this message in error.
======================================================
Any ideas on how to work with the administrative projects?
I just recently upgraded towards MSP Server 2003. I get
stuck now on working with administrative / non-working
time. This option seems not to be available. The
following message occurs when using "Notify your manager
of time you will not be available for project work":
======================================================
You are not assigned to any tasks on any administrative
project, such as vacation, sick, or bereavement.
To submit time against an administrative project, you
must be assigned to a task on that project for the time
period that you are unavailable for project work.
Contact your server administrator if you feel you have
received this message in error.
======================================================
Any ideas on how to work with the administrative projects?